The
East River Environmental Control Centre(ERECC) serves the Towns
of Westville, Stellarton, New Glasgow and Trenton as well as a number
of adjacent urbanized areas in the Municipality of the County of
Pictou. The system includes a central sewage treatment plant, approximately
16 km of sewer lines and 17 pumping stations and about 6 km of pressure
sewers. The treatment plant is located on the east bank of the East
River near the Trenton/New Glasgow town boundary. The plant was
constructed in the early 1970's and has been upgraded in the 1990's.
The Pictou County District Planning Commission operates and maintains
the system through the Regional Services District 2 (RSD2) Committee,
which consists of the mayor/warden and one councilor from each of
the five municipal units.
Unit Processes within the treatment facility include grit extraction,
screening, aeration, secondary clarification, and effluent disinfection
using chlorine. All flows up to 25m³/min receive full secondary
treatment through this process train. Flows in excess of 25 m³/min
receive only primary clarification prior to disinfection. Primary
and waste activated biosolids generated in the treatment process
are aerobically digested and subsequently dewatered using solid
bowl centrifuges. Dewatered biosolids are subsurface injected on
agricultural land in the surrounding area.
|